Print Page   |   Contact Us   |   Your Cart   |   Sign In   |   Join Now
[INFO4B2G] Useful Information for B2G Companies
Blog Home All Blogs
Search all posts for:   

 

View all (70) posts »
 

Excusable Delays (Government Contracts)

Posted By Tom Petruska, Thursday, December 30, 2010

Excusable Delays

When a company enters into a contract with the government, it is required to comply strictly with the terms and conditions of the contract. As with every rule, there is an exception called an excusable delay. An excusable delay is equivalent to an event of "Force Majeure” in commercial contracts. An authorized excusable delay serves to shield the contractor from adverse actions such as liquidated damages, default, and other damages.

A contractor is not empowered to define an excusable delay. The reasons for an excusable delay are found in the contract clauses. Such a delay must be beyond the (foreseeable) control of the contractor, or could not be prevented or overcome. In addition, it must have occurred without the contractor’s fault or negligence. There are several enumerated causes of delay in the contract clauses, and to some rare non-enumerated causes of delay shch as impossibility of performance unknown to the contractor at the time of contract formation, or financial distress caused by the government.

The limitation or restraint on the use of excusable delay is intended to stress that the contractor is required to perform the contract that resulted from their proposal is strict compliance with those contract terms and conditions.

The issue of excusable delay was discussed in the opinion from the United States Civilian Board of Contrat Appeals (the "CBCA” or the "Board”) in the appeal of Siver Spring Citrus, Inc. ("SSCI”) v. Department of Agriculture ("USDA”) CBCA 1659, August 4, 2010.

In 2008, SSCI received seven separate contracts for canned fruit juice. The contracts contained a clause for liquidated damages generally for $.15 per hundred weight per calendar day not to exceed 45 days of delay unless the delay was excusable under the excusable delay clause in the contract.

Subsequently, SSCI experienced sporadic problems with various equipment requiring extensive repairs and resulting in downtime. For these reasons, SSCI claimed excusable delay for their inability to make timely deliveries. The Contracting Officer rejected the SSCI excuses and assessed liquidated damages.

The Board had no sympathy for SSCI observing that "an excusable failure to deliver timely occurs when the failure is caused by an occurrence beyond the reasonable control of the contractor and without its fault or negligence.” The CBCA then stated that "SSCI’s delays were ascribed to equipment and mechanical malfunctions. Neither an equipment malfunction nor a mechanical malfunction is a valid excuse for a delay.” The Board went on to explain that "the inability to make [timely deliveries] because of equipment and mechanical malfunction is not extraneous to the contract, and it is therefore not an excusable delay.”

The moral of the story is a contractor must strictly comply with the terms and conditions of a contract.

In a given situation, an excusable delay may be possible if and only if the delay conforms to the acquisition regulation contract clauses. Contractor developed excuses will never be accepted by the government.

Tom Petruska

Contracts Unlimited, Incorporated

The foregoing discussion is not intended to be legal advice or a legal opinion. Please see your attorney for legal support.

#B2GEDU

[B2GEDU]

Tags:  CONTRACTS  EXCUSBALE DELAYS 

Share |
Permalink | Comments (0)
 
Association Management Software Powered by YourMembership.com®  ::  Legal